Is 4 L of China Orampadu-Renigunta section of NH-716 Package-II of Kadapa- Renigunta section finished?
Cuddapah road works: work going on, Annamayya, Tirupati. Cost as printed ₹1,500.11 crore. From MoSPI report, August 2026, with the paper linked.
- 4 L of China Orampadu-Renigunta section of NH-716 Package-II of Kadapa- Renigunta section
- Kind of work: Roads
- Status in the record: Work going on
- Place: Annamayya, Tirupati
- Cost as printed: ₹1,500.11 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 2.3%
- Expected completion as printed: 1 March 2028
- Department: Roads & Highways
- Paper: MoSPI report, August 2026
- Papers on record from 1 December 2022 to 31 August 2026
- More works in Annamayya district
- NH-440 road works
- Madanapalli road works
- Cuddapah road works
- More works in Tirupati district
- Naidupeta road works
- Chillakuru cross road to Turpu KanupurPart
- NH-716B road works
- Naidupeta road works
The full page is loading. Every number here is from a government paper.