Naidupeta road works: work going on, Tirupati. Cost as printed ₹2,510.14 crore. From MoSPI report, August 2026, with the paper linked.
- Renigunta - Poyya - Naidupeta km 124.60 to km 183.4 of NH 71
- Kind of work: Roads
- Status in the record: Work going on
- Place: Tirupati
- Cost as printed: ₹2,510.14 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 98.6%
- Expected completion as printed: 1 September 2026
- Department: Roads & Highways
- Paper: MoSPI report, August 2026