Is 6L Access Controlled Greenfield Highway from Kavulakuntla Ch. 196000 to Narayanmpet Ch. 203500Package-09 finished?
Kavulakuntla to Narayanmpet road works: work going on, Sri Potti Sriramulu Nellore, YSR Kadapa. Cost as printed ₹956.4 crore.
- 6L Access Controlled Greenfield Highway from Kavulakuntla Ch. 196000 to Narayanmpet Ch. 203500Package-09
- Kind of work: Roads
- Status in the record: Work going on
- Place: Sri Potti Sriramulu Nellore, YSR Kadapa
- Cost as printed: ₹956.4 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 54.6%
- Expected completion as printed: 1 December 2027
- Department: Roads & Highways
- Paper: MoSPI report, August 2026
- Papers on record from 1 February 2023 to 31 August 2026
- More works in Sri Potti Sriramulu Nellore district
- Dedicated Port road to Krishnapatnam Port
- Narayanmpet to Chandrasekharpuram road works
- NH-67 road works
- Nellore road works
- More works in YSR Kadapa district
- Nellore road works
- NH-440 road works
- Nandyal road works
- Muddanur to B. Kothapalli section road works
The full page is loading. Every number here is from a government paper.