Is Rehabilitation and Up-gradation of Thimmapuram to Gurajanapalli section from Km 26/150 to Km 41/161 of NH - 214 New NH - 216 to two lane with paved shoulder in the state of Andhra Pradesh under Nhdp-IV finished?
Thimmapuram to Gurajanapalli road works: work going on, Kakinada. Cost as printed ₹432.91 crore. From MoSPI report, August 2026, with the paper linked.
- Rehabilitation and Up-gradation of Thimmapuram to Gurajanapalli section from Km 26/150 to Km 41/161 of NH - 214 New NH - 216 to two lane with paved shoulder in the state of Andhra Pradesh under Nhdp-IV
- Name as printed in the paper: Rehabilitation and Up-gradation of Thimmapuram to Gurajanapalli section from Km 26/150 to Km 41/161 of NH - 214 New NH - 216 to two lane with paved shoulder in the state of Andhra Pradesh under NHDP-IV
- Kind of work: Roads
- Status in the record: Work going on
- Place: Kakinada
- Cost as printed: ₹432.91 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 98.2%
- Expected completion as printed: 1 September 2026
- Department: Roads & Highways
- Paper: MoSPI report, August 2026
- Papers on record from 1 August 2016 to 31 August 2026