Is Development of 4L Road from Samarlakota to Achampeta Junction as part of Kakinada Port Connectivity to NH-16 Rajanagaram Junction in East Godavari District finished?
Kakinada road works: work going on, Kakinada. Cost as printed ₹750.2 crore. From MoSPI report, August 2026, with the paper linked.
- Development of 4L Road from Samarlakota to Achampeta Junction as part of Kakinada Port Connectivity to NH-16 Rajanagaram Junction in East Godavari District
- Kind of work: Roads
- Status in the record: Work going on
- Place: Kakinada
- Cost as printed: ₹750.2 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 93%
- Expected completion as printed: 1 December 2026
- Department: Roads & Highways
- Paper: MoSPI report, August 2026
- Papers on record from 1 May 2023 to 31 August 2026
- More works in Kakinada district
- Thimmapuram to Gurajanapalli road works