Is 4 Laning of NH-544D from Km 37.000 to km 69.000 of Muchukota- Bugga section Pkg-2 finished?
NH-544D road works: work going on, Ananthapuramu. Cost as printed ₹1,055.23 crore. From MoSPI report, August 2026, with the paper linked.
- 4 Laning of NH-544D from Km 37.000 to km 69.000 of Muchukota- Bugga section Pkg-2
- Kind of work: Roads
- Status in the record: Work going on
- Place: Ananthapuramu
- Cost as printed: ₹1,055.23 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 84.9%
- Expected completion as printed: 1 December 2026
- Department: Roads & Highways
- Paper: MoSPI report, August 2026
- Papers on record from 1 October 2022 to 31 August 2026
- More works in Ananthapuramu district
- NH-544DD road works
- Anantapur road works
- Tadipatri road works
- Tadipatri road works
The full page is loading. Every number here is from a government paper.