Is 4 Laning of NH-544D from Km 0.000 to km 37.000 of Anantapur- Muchukota section Pkg-1 finished?
Anantapur road works: work going on, Ananthapuramu. Cost as printed ₹905.98 crore. From MoSPI report, August 2026, with the paper linked.
- 4 Laning of NH-544D from Km 0.000 to km 37.000 of Anantapur- Muchukota section Pkg-1
- Kind of work: Roads
- Status in the record: Work going on
- Place: Ananthapuramu
- Cost as printed: ₹905.98 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 92.3%
- Expected completion as printed: 1 October 2026
- Department: Roads & Highways
- Paper: MoSPI report, August 2026
- Papers on record from 1 October 2022 to 31 August 2026