Is 6L Access Controlled Greenfield Highway from Mallapalle Ch. 176000 to Kavulakuntla Ch. 196000 Package-08 finished?
Mallapalle to Kavulakuntla road works: work going on, YSR Kadapa. Cost as printed ₹751.81 crore. From MoSPI report, August 2026, with the paper linked.
- 6L Access Controlled Greenfield Highway from Mallapalle Ch. 176000 to Kavulakuntla Ch. 196000 Package-08
- Kind of work: Roads
- Status in the record: Work going on
- Place: YSR Kadapa
- Cost as printed: ₹751.81 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 65.9%
- Expected completion as printed: 1 July 2027
- Department: Roads & Highways
- Paper: MoSPI report, August 2026
- Papers on record from 1 February 2023 to 31 August 2026