Is Khammam-Devarapalle Pkg III [4L Access Controlled Greenfield from Chintagudem village to Recherla village Design Chainage 63117 to 105236] finished?
Chintagudem village to Recherla village road works: work going on, District: still being checked in official papers. Cost as printed ₹1,227.07 crore.
- Khammam-Devarapalle Pkg III [4L Access Controlled Greenfield from Chintagudem village to Recherla village Design Chainage 63117 to 105236]
- Kind of work: Roads
- Status in the record: Work going on
- Place: District: still being checked in official papers
- Cost as printed: ₹1,227.07 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 98.8%
- Expected completion as printed: 1 September 2026
- Department: Roads & Highways
- Paper: MoSPI report, August 2026
- Papers on record from 1 January 2021 to 31 August 2026