Is Improvement of 4L road to 6L road and 4L dedicated Port Roads for the Port connectivity road from Convent junction to Sheelanagar Junction finished?
Convent junction to Sheelanagar Junction: work going on, Visakhapatnam. Cost as printed ₹680.21 crore. From MoSPI report, August 2026, with the paper linked.
- Improvement of 4L road to 6L road and 4L dedicated Port Roads for the Port connectivity road from Convent junction to Sheelanagar Junction
- Kind of work: Roads
- Status in the record: Work going on
- Place: Visakhapatnam
- Cost as printed: ₹680.21 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 79%
- Expected completion as printed: 1 December 2026
- Department: Roads & Highways
- Paper: MoSPI report, August 2026
- Papers on record from 1 January 2023 to 31 August 2026
- More works in Visakhapatnam district