Is 6L of Gundugolanu Design km 1023.280 to Kalaparru Design km 1050.680 of NH-5 New NH-16 finished?
NH-5 road works: work going on, District: still being checked in official papers. Cost as printed ₹665.59 crore.
- 6L of Gundugolanu Design km 1023.280 to Kalaparru Design km 1050.680 of NH-5 New NH-16
- Kind of work: Roads
- Status in the record: Work going on
- Place: District: still being checked in official papers
- Cost as printed: ₹665.59 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 95.7%
- Expected completion as printed: 1 August 2026
- Department: Roads & Highways
- Paper: MoSPI report, July 2026
- Papers on record from 1 October 2018 to 31 July 2026
The full page is loading. Every number here is from a government paper.