Has work on Gundrevula Reservoir Project started?
Gundrevula Reservoir Project: approved, District: still being checked in official papers. Cost as printed ₹2,890.55 crore.
- Gundrevula Reservoir Project
- Kind of work: Irrigation
- Status in the record: Approved
- Place: District: still being checked in official papers
- Cost as printed: ₹2,890.55 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 0%
- Department: Water Resources Department, Government of Andhra Pradesh
- Paper: Socio-Economic Survey 2018-19
- Papers on record from 31 March 2019 to 31 March 2019
The full page is loading. Every number here is from a government paper.