Is Modernisation of TBP High Level & Low Level Canals (Tbphlc / Tbpllc) finished?
Modernisation of TBP High Level & Low Level: stopped, Ananthapuramu, Kadapa, Kurnool (as an older paper names it). Cost as printed ₹1,265.88 crore.
- Modernisation of TBP High Level & Low Level Canals (Tbphlc / Tbpllc)
- Name as printed in the paper: Modernisation of TBP High Level & Low Level Canals (TBPHLC / TBPLLC)
- Kind of work: Irrigation
- Status in the record: Stopped
- Place: Ananthapuramu, Kadapa, Kurnool (as an older paper names it)
- Cost as printed: ₹1,265.88 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 68%
- Department: Water Resources Department, Government of Andhra Pradesh
- Paper: Socio-Economic Survey 2024-25
- Papers on record from 31 March 2019 to 31 December 2024