Is Rehabilitation and Upgradation to 2-Lane with Paved Shoulders Configuration of Paderu- Gondiguda Sect finished?
Rehabilitation and Upgradation to 2-Lane: work going on, Asr (as an older paper names it). Cost as printed ₹222.61 crore.
- Rehabilitation and Upgradation to 2-Lane with Paved Shoulders Configuration of Paderu- Gondiguda Sect
- Name as printed in the paper: REHABILITATION AND UPGRADATION TO 2-LANE WITH PAVED SHOULDERS CONFIGURATION OF PADERU- GONDIGUDA SECT
- Kind of work: Roads
- Status in the record: Work going on
- Place: Asr (as an older paper names it)
- Cost as printed: ₹222.61 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 95%
- Expected completion as printed: 1 June 2025
- Department: Road Transport And Highways
- Paper: MoSPI report, June 2025
- Papers on record from 1 August 2020 to 30 June 2025