Is Construction of 2L+PS from Pasarlapudi-Dhindi (105/700 to 127.500 of NH-214) of NH-216 finished?
NH-214 road works: work going on, Dr. B.R. Ambedkar Konaseema. Cost as printed ₹263.45 crore. From MoSPI report, June 2025, with the paper linked.
- Construction of 2L+PS from Pasarlapudi-Dhindi (105/700 to 127.500 of NH-214) of NH-216
- Name as printed in the paper: CONSTRUCTION OF 2L+PS FROM PASARLAPUDI-DHINDI (105/700 TO 127.500 OF NH-214) OF NH-216
- Kind of work: Roads
- Status in the record: Work going on
- Place: Dr. B.R. Ambedkar Konaseema
- Cost as printed: ₹263.45 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 85%
- Expected completion as printed: 1 June 2025
- Department: Road Transport And Highways
- Paper: MoSPI report, June 2025
- Papers on record from 1 January 2017 to 30 June 2025
- More works in Dr. B.R. Ambedkar Konaseema district