Is 2LPS from Gondiguda to Araku Bhallaguda KM 27.480 to KM 51.772 Section of NH 516E finished?
NH-516E road works: work going on, Asr (as an older paper names it). Cost as printed ₹296.66 crore. From MoSPI report, June 2025, with the paper linked.
- 2LPS from Gondiguda to Araku Bhallaguda KM 27.480 to KM 51.772 Section of NH 516E
- Name as printed in the paper: 2LPS FROM GONDIGUDA TO ARAKU BHALLAGUDA KM 27.480 TO KM 51.772 SECTION OF NH 516E
- Kind of work: Roads
- Status in the record: Work going on
- Place: Asr (as an older paper names it)
- Cost as printed: ₹296.66 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 87.5%
- Expected completion as printed: 1 December 2024
- Department: Road Transport And Highways
- Paper: MoSPI report, June 2025
- Papers on record from 1 August 2020 to 30 June 2025