Is NH-30-Bhadrachalam to Konta Section 2LPS finished?
NH-30 road works: work going on, Asr (as an older paper names it). Cost as printed ₹388.71 crore. From MoSPI report, June 2025, with the paper linked.
- NH-30-Bhadrachalam to Konta Section 2LPS
- Name as printed in the paper: NH-30-BHADRACHALAM TO KONTA SECTION 2LPS
- Kind of work: Roads
- Status in the record: Work going on
- Place: Asr (as an older paper names it)
- Cost as printed: ₹388.71 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 89.6%
- Expected completion as printed: 1 September 2025
- Department: Road Transport And Highways
- Paper: MoSPI report, June 2025
- Papers on record from 1 December 2021 to 30 June 2025
The full page is loading. Every number here is from a government paper.