Is Widening to two lane with paved shoulders from Km 0/0 to 64/020 Pamarru to Akiveedu finished?
Akiveedu road works: work going on, Eluru, Krishna, West Godavari. Cost as printed ₹588.65 crore. From MoSPI report, August 2026, with the paper linked.
- Widening to two lane with paved shoulders from Km 0/0 to 64/020 Pamarru to Akiveedu
- Kind of work: Roads
- Status in the record: Work going on
- Place: Eluru, Krishna, West Godavari
- Cost as printed: ₹588.65 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 74.4%
- Expected completion as printed: 1 May 2027
- Department: Roads & Highways
- Paper: MoSPI report, August 2026
- Papers on record from 1 March 2020 to 31 August 2026