Is Bangalore Chennai Expressway Phase-II Pkg-I from km.71.000 to Km 96.000 Bethamangala in the state of Karnataka to Byreddypalli finished?
Bangalore Chennai Expressway: work going on, Chittoor. Cost as printed ₹1,410.01 crore. From MoSPI report, August 2026, with the paper linked.
- Bangalore Chennai Expressway Phase-II Pkg-I from km.71.000 to Km 96.000 Bethamangala in the state of Karnataka to Byreddypalli
- Kind of work: Roads
- Status in the record: Work going on
- Place: Chittoor
- Cost as printed: ₹1,410.01 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 99.2%
- Expected completion as printed: 1 September 2026
- Department: Roads & Highways
- Paper: MoSPI report, August 2026
- Papers on record from 1 December 2020 to 31 August 2026