Is Doubling between Gooty-Pendakallu 29.225 km PB73/2023-24/NR finished?
Gooty road works: work going on, District: still being checked in official papers. Cost as printed ₹351.83 crore.
- Doubling between Gooty-Pendakallu 29.225 km PB73/2023-24/NR
- Kind of work: Railways
- Status in the record: Work going on
- Place: District: still being checked in official papers
- Cost as printed: ₹351.83 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 45%
- Expected completion as printed: 1 March 2027
- Department: Railways
- Paper: MoSPI report, August 2026
- Papers on record from 1 March 2023 to 31 August 2026