Is Penukonda-Dharmavaram, Excl. Dharmavaram (41.5 KM) finished?
Dharmavaram road works: work going on, District: still being checked in official papers. Cost as printed ₹307.66 crore.
- Penukonda-Dharmavaram, Excl. Dharmavaram (41.5 KM)
- Name as printed in the paper: PENUKONDA-DHARMAVARAM, EXCL. DHARMAVARAM (41.5 KM)
- Kind of work: Railways
- Status in the record: Work going on
- Place: District: still being checked in official papers
- Cost as printed: ₹307.66 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 60%
- Expected completion as printed: 1 December 2025
- Department: Railways
- Paper: MoSPI report, June 2025
- Papers on record from 1 April 2019 to 30 June 2025
The full page is loading. Every number here is from a government paper.