Is Kottavalasa-Koraput 189.278 km finished?
Kottavalasa-Koraput 189.278 km: work going on, Vizianagaram, Vishakaphatnam (as an older paper names it). Cost as printed ₹3,580.41 crore.
- Kottavalasa-Koraput 189.278 km
- Kind of work: Railways
- Status in the record: Work going on
- Place: Vizianagaram, Vishakaphatnam (as an older paper names it)
- Cost as printed: ₹3,580.41 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 74%
- Expected completion as printed: 1 March 2028
- Department: Railways
- Paper: MoSPI report, August 2026
- Papers on record from 1 April 2015 to 31 August 2026