Is Kotlpalli-Narasapur (Nl) finished?
Narasapur railway works: work going on, District: still being checked in official papers. Cost as printed ₹2,500.98 crore.
- Kotlpalli-Narasapur (Nl)
- Name as printed in the paper: KOTLPALLI-NARASAPUR (NL)
- Kind of work: Railways
- Status in the record: Work going on
- Place: District: still being checked in official papers
- Cost as printed: ₹2,500.98 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 18%
- Expected completion as printed: 1 March 2027
- Department: Railways
- Paper: MoSPI report, June 2025
- Papers on record from 1 December 2001 to 30 June 2025