Is Transmission System for Integration of Kurnool-IV REZ Phase-I [for 4.5 GW] [Powergrid Kurnool-IV Transmission Limited] finished?
Kurnool power lines: work going on, District: still being checked in official papers. Cost as printed ₹5,550 crore.
- Transmission System for Integration of Kurnool-IV REZ Phase-I [for 4.5 GW] [Powergrid Kurnool-IV Transmission Limited]
- Name as printed in the paper: Transmission System for Integration of Kurnool-IV REZ Phase-I [for 4.5 GW] [POWERGRID Kurnool-IV Transmission Limited]
- Kind of work: Power
- Status in the record: Work going on
- Place: District: still being checked in official papers
- Cost as printed: ₹5,550 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 34.5%
- Expected completion as printed: 1 September 2027
- Department: Transmission & Distribution
- Paper: MoSPI report, August 2026
- Papers on record from 1 March 2025 to 31 August 2026