Is Hp Trijet Unit in Vr finished?
Tuni industrial project: work going on, District: still being checked in official papers. Cost as printed ₹193 crore.
- Hp Trijet Unit in Vr
- Name as printed in the paper: HP TRIJET UNIT IN VR
- Kind of work: Industry
- Status in the record: Work going on
- Place: District: still being checked in official papers
- Cost as printed: ₹193 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 23%
- Expected completion as printed: 1 July 2027
- Department: Petroleum
- Paper: MoSPI report, June 2025
- Papers on record from 1 July 2024 to 30 June 2025