Is Construction of New Domestic Terminal Building at Rajahmundry Airport finished?
Rajahmundry airport works: work going on, East Godavari. Cost as printed ₹347.15 crore. From MoSPI report, August 2026, with the paper linked.
- Construction of New Domestic Terminal Building at Rajahmundry Airport
- Name as printed in the paper: Construction of New Domestic Terminal Building at Rajahmundry Airport.
- Kind of work: Airports
- Status in the record: Work going on
- Place: East Godavari
- Cost as printed: ₹347.15 crore. This is the estimate in that paper, not money spent.
- Physical progress as printed: 97%
- Expected completion as printed: 1 October 2026
- Department: Aviation & Aviation Infrastructure
- Paper: MoSPI report, August 2026
- Papers on record from 1 December 2022 to 31 August 2026
- More works in East Godavari district