Is Providing Sewerage scheme in Ananthapuramu Municipal Coporation Municipality under AMRUT 2.0, Anantapur finished?
Anantapur sewage works: work going on, Ananthapuramu. Cost as printed ₹70.29 crore.
- Providing Sewerage scheme in Ananthapuramu Municipal Coporation Municipality under AMRUT 2.0, Anantapur
- Name as printed in the paper: Providing Sewerage scheme in Ananthapuramu Municipal Coporation Municipality under AMRUT 2.0 — Anantapur
- Kind of work: Towns and cities
- Status in the record: Work going on
- Place: Ananthapuramu
- Cost as printed: ₹70.29 crore. This is the estimate in that paper, not money spent.
- Expected completion as printed: 1 December 2027
- Department: Urban Development — AMRUT 2.0 (MoHUA)
- Paper: AMRUT list, Union Housing and Urban Affairs Ministry
- More works in Ananthapuramu district
- Guntakal water supply
- Rayadurg urban works
- Tadipatri sewage works
- Rayadurg housing
The full page is loading. Every number here is from a government paper.