Is Rejuvenation of water bodies (Pirangula Dibba), Eluru finished?
Eluru water body works: work going on, Eluru. Cost as printed ₹1.5 crore. From AMRUT list, Union Housing and Urban Affairs Ministry, with the paper linked.
- Rejuvenation of water bodies (Pirangula Dibba), Eluru
- Name as printed in the paper: Rejuvenation of water bodies (Pirangula Dibba) — Eluru
- Kind of work: Towns and cities
- Status in the record: Work going on
- Place: Eluru
- Cost as printed: ₹1.5 crore. This is the estimate in that paper, not money spent.
- Expected completion as printed: 1 September 2026
- Department: Urban Development — AMRUT 2.0 (MoHUA)
- Paper: AMRUT list, Union Housing and Urban Affairs Ministry
- More works in Eluru district
- Eluru Pumpula Cheruvu
- Eluru Ponangi Pedda Cheruvu
- Eluru Kotha Cheruvu
- Eluru water body works
The full page is loading. Every number here is from a government paper.