Is Development of Lake in Gollaprolu Nagar Panchayat finished?
Gollaprolu urban works: work going on, Kakinada. Cost as printed ₹4.1 crore. From AMRUT list, Union Housing and Urban Affairs Ministry, with the paper linked.
- Development of Lake in Gollaprolu Nagar Panchayat
- Kind of work: Towns and cities
- Status in the record: Work going on
- Place: Kakinada
- Cost as printed: ₹4.1 crore. This is the estimate in that paper, not money spent.
- Expected completion as printed: 1 September 2026
- Department: Urban Development — AMRUT 2.0 (MoHUA)
- Paper: AMRUT list, Union Housing and Urban Affairs Ministry
- More works in Kakinada district
- Samalkot water supply
- Gollaprolu water supply
- Samalkot water supply
- Tuni water supply
The full page is loading. Every number here is from a government paper.